Building Works Update 12/06/2019

637580_1124x

Published 06:27 on 5 Jun 2019

Building Works Update 12 6 19

Following another productive week, this weeks progress includes;

The Titan lift was delivered on Monday and the installation will be completed by the end of the week.

The new loft hatch and ladder has been installed and the loft will be boarded for use as storage.

The doorway to the club room is being enlarged ready for the new light oak and glass double doors to be installed.

The new doors to the galley and disabled toilet will be fitted.

Members are reminded that the bar and catering will remain open during the build, access to the Clubroom remains via the balcony doors.

The ladies and gents toilets and showers will be open at weekends but will be closed during the week. Portaloos are in place and the visitors toilet and shower is available. There is a Portakabin for use as a changing room. The car park will remain open but as spaces are restricted it is important that care should be taken to park within the designated spaces. To assist, cars can be reversed parked against the builders metal fence. The rear car park is open.

We continue to appreciate your co-operation during the build.

Building Works Update 4 6 19

Following further excellent progress last week, this week will include:

The new main staircase carcass has been installed, finishing off to take place.

The new short staircase to the tea/coffee galley will be installed.

The lift pit will be excavated for the lift to be installed next week.

The door opening to the ladies and gents toilets will be completed.

The ceiling of the new meeting/lounge room will be plastered.

Members are reminded that the bar and catering will remain open during the build, access to the club room is via the balcony doors.

The ladies and gents toilets and showers will be open at weekends but will be closed during the week. Portaloos are in place and the visitors toilet and shower is available. There is a Portakabin for use as a changing room.

The car park will remain open but as spaces are restricted it is important that care should be taken to park within the designated spaces. To assist, cars can be reverse parked against the builders metal fence. The rear car park is open.

We continue to appreciate your co-operation during the build.